Estadio Deportivo
NEWS
NEWS
Estadio
Deportivo
The project consists of building a multi-sport stadium with capacity for XX people.
The objective is to build a cultural project that positively impacts the local community. The cultural importance of the project shows how AINCOcan work with all stakeholders to ensure the success of a project in high-risk projects.
Project log
An emblematic project for the community; as a cultural project it has great relevance in the socio-political context of the area. At AINCO, we have the ability to handle high-impact projects with good management of socio-environmental resources. Constructively, the stadium consists of two grandstands, an athletics track and a soccer field built to international standards.
Interested Entities
The project is carried out for the benefit of our client O.N.G. A.D.I.F.C.O., which hires AINCO for the construction of the project of vital importance to the local city.
Customer
O.N.G. ADIFCO
Measures
2 grandstands with a capacity for 20 thousand spectators, an athletics track and a soccer field with all international standards.
Location
Huehuetenango, Huehuetenango, Guatemala.
Photo gallery





NEWS
AINCO CONSTRUCTION PROCESS METHODOLOGY
PROJECT MANAGEMENT
Project management was a challenge because of risks such as inflation and its effect on the project: given the geopolitical context at the time of the bid, there could be a significant variation when making the respective purchases and expenses during the project that would harm it. Good financial and procurement management would determine the success of the project.
LEAN
A LEAN philosophy of continuous improvement was the main focus of the project. It demonstrated the importance of digital tools to improve the efficiency of internal construction processes, and of LEAN lossless construction tools to ensure a PULL approach to progress on site.
Quality management
There were 6 communication channels, which were subdivided much further because of the large number of members in each stakeholder, so the project manager had to convey and communicate the status of the project to all parties in the best possible way.
Look Ahead
The LOOK AHEAD tool was implemented as the main planning communication method among all parties in order to achieve lossless construction and coordinate events outside the scope of AINCO.
Coaspect
Implementation of PMIS software for cloud-based project management under the PMI methodology, which made it possible to keep a digital log of all internal and external processes for AINCO's control and for follow-up by all stakeholders.
Last Planner System
With the LPS tool we were able to coordinate work trains with the supervisor and have a better perspective when the project faced challenges.
BIM
BIM uses were established mainly for the metal structure, the visualization of steel material and the coordination of fabrication, transport and assembly.
Fabrication
Modeling this construction element requires specific knowledge of the fabrication method to be used, so it was crucial to have synchronization between design, modeling and fabrication.
As Built
Having an As Built model allows all stakeholders to view all of the project's information during the different stages of the project, for its operation and maintenance stage.
IPD
A collaborative contract was made in which the project's financial risk was shared, construction needs were established based on the real needs of the project and its users. Changes were established and their costs and benefits were assumed by all parties, always keeping the quality and functionality of the final product as a priority for everyone.
Project Amount
USD 235,000.00
Contract Type
Design - Bid - Build
Aprobado
Work acceptance records signed by all stakeholders.
AINCO METHODOLOGY
4D Y 5D
Construction
Construction began on January 17, 2022, under Resident Engineer Walfred Colindres, who moved to the area with AINCO personnel, where the first preliminary work began: clearing the area, setting up a storage area, topographic layout, and logistics tests with SAT so as not to stop customs operations, along with site signage for the safety of all parties.
Because construction began on an active stretch of road, many precautions were taken for site safety: SAT provided the safety barriers used at the customs office and AINCO also placed tapes and signs intended to guarantee the safety of everyone traveling through the area.
During the topographic layout, our surveying team detected a variation between the field and the design: the terrain was shown as flat in the design, but a slope was measured, so a zero point had to be determined so that the 4 pillars of the structure would remain on the same reference plane. This difference between design and reality is very important because it could have affected the integrity of the project, both constructively and financially; however, the AINCO team quickly identified the discrepancy and resolved it at the right time.
Consequently, excavation of axis B began, with work starting under the logistical restrictions set by SAT and the need to keep the lanes open, even though the foundation axes were located directly in the lanes. This affected our initial planning schedule.
On January 31 the work was stopped because of a restriction outside the scope of AINCO, in which a utility pole did not allow the work to continue. The site was closed, AINCO's equipment was withdrawn, and AINCO supported at all times and offered solutions to resolve the project's restriction. This stoppage has financial, operational and organizational costs; all stakeholders were affected in one way or another.
Lecciones aprendidas